Holmhurst Gardens
Southern Housing is one of the largest housing providers in the UK with around 80,000 homes across London, the South East, the Isle of Wight and the Midlands, giving over 167,000 people somewhere affordable to call their own.
Our vision is to create and support communities where everyone has a safe home in a place where they’re proud to live.
Keeping you updated about your new home
We look forward to welcoming you to your new home at Holmhurst Gardens Whilst we're doing all we can to make that happen as quickly as possible, we also recognise the stress andContinue reading
Southern Housing is one of the largest housing providers in the UK with around 80,000 homes across London, the South East, the Isle of Wight and the Midlands, giving over 167,000 people somewhere affordable to call their own.
Our vision is to create and support communities where everyone has a safe home in a place where they’re proud to live.
Keeping you updated about your new home
We look forward to welcoming you to your new home at Holmhurst Gardens Whilst we're doing all we can to make that happen as quickly as possible, we also recognise the stress and inconvenience many buyers are experiencing as you wait to move into your new home.
We've committed to providing buyers with a progress updates by email. In addition, we'll keep you informed on this webpage with updates and answers to frequently asked questions.
How to use the webpage
You'll find these tools by scrolling down and clicking on the following tabs:
- Your questions - here you can ask a question and read what other people have asked.
- Updates - Read the latest fortnightly update and look back over previous updates.
The following features can be found to the right of your screen (or by scrolling down if using a hand-held device).
- Who's listening - contact details for members of the team who monitor this webpage and who you can email if you prefer your query to remain private.
- Key milestones - A timeline of key milestones, tracking progress towards occupation.
- FAQs - We'll add responses to frequently asked questions here, so these will evolve over time.
- Photos - We'll add the latest photos showing progress on site here.
- Glossary of terms - abbreviations, technical language and jargon explained in more detail here. If you come across a term you're not familiar with, please message us.
- Holmhurst newsletter - this is a newsletter that we've produced about the development, it contains some interesting information and drone footage of the site.
- Document library – for useful documents.
Languages
The webpage can be translated into dozens of different languages. If you or a family member would find it helpful, click on Select Language to the top left of your screen (the globe icon). Please note it won't translate documents in the Document Library.
We'll add more information as it becomes available and in response to your requests. Please note there may be periods when the webpage is not available while we update information. If so, please try again later.
-
Update 22/10/25
Share Update 22/10/25 on Facebook Share Update 22/10/25 on Twitter Share Update 22/10/25 on Linkedin Email Update 22/10/25 linkI am pleased to confirm that the damp proof course issue has been successfully rectified. Building Control has signed off the units and we are awaiting their final certificate. All other outstanding certificates required for us to take handover have now been received.
Our Clerk of Works is visiting site again this Friday 24 October with a view to signing off the units. Internal handover has been booked for 28 October.
As soon as we receive confirmation of handover, we will serve notice to complete via your solicitors. Your solicitor will then contact you to arrange a date for completion within the 10-day notice period in line with your contract.
If for any reason the Clerk of Works reports anything from his visit on Friday, that will affect the proposed handover dates, we will be in touch again. If all goes to plan your solicitor will be in touch following handover. I am on leave next week but my colleague Joanne, copied into this email will update you all as soon as we hear any news on Tuesday.
If you have any questions, then please do not hesitate to contact us.
-
Update 16/10/2025
Share Update 16/10/2025 on Facebook Share Update 16/10/2025 on Twitter Share Update 16/10/2025 on Linkedin Email Update 16/10/2025 linkWe are writing to provide you with an update on the anticipated handover date.
Our Clerk of Works visited the site this week, snagging and de-snagging works are continuing throughout your homes, and they are due to reinspect again tomorrow with a view to signing off the items raised. We have two clerk of works attending and inspecting the plots to try and expediate things.
We have been informed by the contractor that Building Control has flagged an issue with the damp proof course in the homes. Further work is required to correct this, and we cannot legally take handover until we have final sign-off from Building Control. As such, it is looking unlikely that the properties will be ready for handover next Tuesday as planned.
A new predicted date of 28 October has been given for handover, but the clerk of works will visit again tomorrow and early next week to inspect the homes and will continue to visit and provide us with frequent updates as to whether the new predicated date is achievable.
We know how incredibly frustrating this news is going to be. Please rest assured that we are doing everything we can to push for the completion of your homes.
We will provide another update by Wednesday 22 October, however if you have any questions then please do not hesitate to contact us.
-
Update 09/10/2025
Share Update 09/10/2025 on Facebook Share Update 09/10/2025 on Twitter Share Update 09/10/2025 on Linkedin Email Update 09/10/2025 linkI am emailing to update you following the recent inspection at Holmhurst Gardens.
The clerk of works (CoW) visited the site this week and has identified some outstanding decorative snagging items that the contractor will need to address before we can proceed with handover. Additionally, there is still some external work to be completed.
A follow-up inspection is scheduled for 14 October. Based on the outcome of that visit, the CoW will assess whether the projected handover date of 21 October remains achievable. Please note that this timeline also depends on the final quality checks of your home and the completion of all necessary legal documentation.
We will be in touch again by Thursday 16 October with the outcome of the inspection and any further updates.
In the meantime, if you have any questions or concerns, please don’t hesitate to contact us via the contact details on this webpage or the questions tab.
-
Update 19/09/2025
Share Update 19/09/2025 on Facebook Share Update 19/09/2025 on Twitter Share Update 19/09/2025 on Linkedin Email Update 19/09/2025 linkGood afternoon,
I am emailing to provide you with an update on progress at Holmhurst Gardens.
I am sorry to inform you that the completion of plots 90-96 has been delayed again. This is due to the final commissioning of the air source heat pumps. This affects certificates being issued which delays the final building control sign off, we must have this to accept handover of the homes.
The snagging of your property is now scheduled to take place on 7 October 2025. Once this is complete, we will be in a much better position to provide you with a new completion date.
We sincerely apologise for this further delay. We will continue to get updates from the team and will be in touch again by Friday, 10 October 25, with another update.
Who's Listening
-
Phone 0300 555 2171 Email sales@southernhousing.org.uk -
Phone 0300 555 2171 Email sarah.dodd@southernhousing.org.uk
Key milestones
-
Practical Completion
Holmhurst Gardens is currently at this stageThis is when Southern Housing will receive the homes from the contractors
-
Sales Team serves notice to complete
this is an upcoming stage for Holmhurst GardensOur solicitors serve notice to purchasers’ solicitors advising we are ready to complete the sale. Your solicitor will agree a specific move in date on your behalf.
-
Occupation
this is an upcoming stage for Holmhurst GardensCustomers move in within 10 working days of notice being served