Greenside, Alton Road

Share Greenside, Alton Road on Facebook Share Greenside, Alton Road on Twitter Share Greenside, Alton Road on Linkedin Email Greenside, Alton Road link
Greenside site plan


Southern Housing is one of the largest housing providers in the UK with around 80,000 homes across London, the South East, the Isle of Wight and the Midlands, giving over 167,000 people somewhere affordable to call their own.

Our vision is to create and support communities where everyone has a safe home in a place where they’re proud to live.

Keeping you updated about your new home

We look forward to welcoming you to your new home at Greenside. Whilst we're doing all we can to make that happen as quickly as possible, we also recognise the stress and inconvenience


Southern Housing is one of the largest housing providers in the UK with around 80,000 homes across London, the South East, the Isle of Wight and the Midlands, giving over 167,000 people somewhere affordable to call their own.

Our vision is to create and support communities where everyone has a safe home in a place where they’re proud to live.

Keeping you updated about your new home

We look forward to welcoming you to your new home at Greenside. Whilst we're doing all we can to make that happen as quickly as possible, we also recognise the stress and inconvenience many buyers are experiencing as you wait to move into your new home.

We've committed to providing buyers with a progress update by email every other Wednesday. In addition, we'll keep you informed on this webpage with updates and answers to frequently asked questions.

How to use the webpage

You'll find these tools by scrolling down and clicking on the following tabs:

  • Your questions - here you can ask a question and read what other people have asked.
  • Updates - Read the latest fortnightly update and look back over previous updates since July 2024.
  • Ideas - A place for you to share your ideas for how to improve the webpage.

The following features can be found to the right of your screen (or by scrolling down if using a hand-held device).

  • Who's listening - contact details for members of the team who monitor this webpage and who you can email if you prefer your query to remain private.
  • Key milestones - A timeline tracking progress towards occupation.
  • FAQs - We'll add responses to frequently asked questions here, so these will evolve over time.
  • Glossary of terms - abbreviations, technical language and jargon explained in more detail here. If you come across a term you're not familiar with, please message us using the Ideas tab below.
  • Document library - here we’ll store minutes of meetings, brochures, previous FAQs etc. Please let us know if there are any published documents you'd like us to save here (see Ideas).
  • Photos - We'll add the latest photos showing progress on site here.

Languages

The webpage can be translated into dozens of different languages. If you or a family member would find it helpful, click on Select Language to the top left of your screen (the globe icon). Please note it won't translate documents in the Document Library.

We'll add more information as it becomes available and in response to your requests. Please note there may be periods when the webpage is not available while we update information. If so, please try again later.

  • 16 July update and meeting invitation

    Share 16 July update and meeting invitation on Facebook Share 16 July update and meeting invitation on Twitter Share 16 July update and meeting invitation on Linkedin Email 16 July update and meeting invitation link

    Good afternoon,

    I hope you are all keeping well. I email with the latest development update regarding Greenside.

    First, we are pleased to confirm we will be holding another update at 5.30pm, 30 July, via Teams.

    The Southern Housing Sales and Development Directors will be in the meeting along with the other representatives from the team. A representative from Censeo (one of our panel of mortgage advisors) will also be there to any general questions regarding mortgages.

    At the meeting we will be providing the latest position as we move towards practical completion. If you have any specific questions, please let me and Sarah know in advance, and we will prepare responses for the meeting.

    Please be reminded that others on the call will be able to see your name etc.

    I’d like to take this opportunity to give you a quick site progress update:

    All Blocks

    • Lobby and canopy work is underway. We are predicting this work will be complete within the next four weeks.
    • Blocks A & D are nearing completion and getting ready for the Clerk of Work snagging.


    Block B

    Currently being de-snagged, except for the basement properties.

    Block B Basement properties:

    • Plots B1 and B2: flooring is being laid and nearing contractor’s snag.
    • Plot B5: 2nd fix being completed, flooring being laid, decorating nearly complete.
    • Communal areas tape and jointing, 2nd fix carpentry nearly done.
    • Fencing going up in the basement gardens.


    Block C:

    Ground – 4th floor snagging is nearly complete. Mulalley is completing the snagging items in these properties ready for de-snag.

    Block C Basements properties:

    • C07- Living area stripped back to ascertaining water ingress source. Specialist employed to help rectify this. Bathrooms near completion, kitchen installed and flooring will be installed once water ingress rectified.
    • C06 - Kitchen fitted and wood flooring installed. 2nd fix carpentry and electrical mostly complete.
    • C08 - 2nd fix mostly complete with decoration mostly complete. Not affected by water ingress.


    General

    • Lots of activity on site.
    • Lifts were being tested 10 July ready for commissioning.
    • The draft operational and mechanical manual has been received ready to review.
    • Pre-occupational fire risk assessment is due to be carried out at the beginning of August.
    • Energy Performance Certificates are ready and due to be issued.
    • A non-material amendment has been agreed by the local authority to allow occupation prior to all 278 works being completed.
    • Virgin Media installation (under 278 works) has been instructed and paid for. We await installation date.


    Practical Completion and handover

    Mulalley is predicting practical completion 27 August.

    We anticipate BSR sign off in September.

    We anticipate internal handover to the sales team mid-September.

    We anticipate occupations from late September. This is not guaranteed and is subject to change.