Update 25/09/2024
Good afternoon,
I hope you are all well and looking forward to visiting your home on the 9th of October.
At the moment we still have no official handover date confirmed. Our Development Manager and our Employers Agent are still anticipating handover at the end of October/beginning on November. Kindly find the latest update regarding Holmhurst Gardens below:
- The correct street lighting has now been installed.
- Snagging is still proving to be a challenge, with our Clark of Works yet to confirm any property is ready for inspection/handover to the Sales Team.
- We are trying to achieve a two-week notice (this means we would be scheduled to take practical completion of the homes in two weeks), but this is subject to the homes being snag free.
- There has been a verbal agreement with the local planning authority confirming that the play areas in phase 1 can be installed at a later date due to health and safety concerns. We need this in writing. We await this confirmation from the local authority confirming but this could be a risk to handover.
Personally, my opinion has not changed and you could potentially move into your homes after Christmas. I am hopeful we can better this date if snagging is improved.
Our Pre-Sales Manager is visiting site again today to check on progress.
I am on leave from next Friday (4th of October) for two weeks. I will endeavour to get you an interim update by Thursday 3rd of October and will send another update when I return by the 25th of October. Sarah or Adina will update you if we take handover in this interim period.
Kind regards
Thank you for your contribution!