Update 07/11/2024

Good afternoon,

Please find below our latest update on progress at Holmhurst Gardens:

Handovers

I am really pleased to confirm plots 31-34 handed over last week.

Plots 10 and 11 handed over 5 November 2024 and plots 35 and 36 are due to handover next week subject to our final quality check on the 12th November 2024.

The next inspections for plots 16-30 are taking place throughout November 2024. If we are satisfied with the finish as they are inspected, then we may accept handover and will update you regarding occupation straight away.

Please note, we will only accept the homes if we are satisfied with the finish.

Plots 73, 74, 75, 76, 77, 78, 79, 80, 81, 88, 89, 50, 51, 52, 53, 54, 55, 56, 57, 58 and 59 we are still predicting will handover in the New Year, however this is under constant review and we will update you with any changes.

Next update

The next update will be sent to you by 21 November 2024 but we will provide an interim update to the buyers of plots 35 and 36 once they have been inspected on 12 November 2024.

You can contact us by email at sales@southernhousing.org.uk or by asking a question via the ‘questions’ tab on this page.

Share Update 07/11/2024 on Facebook Share Update 07/11/2024 on Twitter Share Update 07/11/2024 on Linkedin Email Update 07/11/2024 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>