Please find below our latest update on progress at Holmhurst Gardens:

Handovers

I am pleased to confirm that plots 23, 24, 26, 28, 35 and 36 have now handed over.

Plots 25, 50-51 and 73-76 are being inspected today, however we have not received building control certificates and so we will not be taking handover of these plots today. Our construction team will return to site tomorrow with a view to taking handover, but this will be subject to receiving the building control certificates. Please note that if handover is delayed past 10th December, the next available handover date will be in January. This is crucial to ensure sufficient time for legal processes, including your solicitor's request for funds from your lender. We will only accept the homes once the inspections confirm that the contractor has fulfilled the contractual level of finish.

Plots 52-59, 77-81 and 88 & 89 are still predicted for handover in the New Year. We expect to start taking handover from mid-January due to site closure over Christmas.

Next update

We will update the buyers of the plots being inspected on Friday by Monday 9th December. For all other plots, your next update will be by 17th January 2025.

If you have any questions relating to your specific circumstances then please do continue to speak to your sales progressor, Sarah. Otherwise, you can get in touch with us via the questions tab on this page.

Share Update 05/12/2024 on Facebook Share Update 05/12/2024 on Twitter Share Update 05/12/2024 on Linkedin Email Update 05/12/2024 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>