Update 22.08.2025
Good morning,
We have received a number of questions via Engagement HQ and direct emails following last week’s update. To ensure we can effectively focus on the critical path to Practical Completion (PC) and occupation, we are clarifying our communication approach.
We’ll continue to provide updates on the key items and dependencies that are critical to PC and occupation — these will be shared in the table format you’re familiar with.
To stay focused, we won’t be responding to detailed questions about the underlying elements of those headline items. We’re currently receiving a high volume of very detailed queries, which is making it harder for us to concentrate on holding the contractor accountable and progressing the work needed for PC and occupation.
Please rest assured that we’re always doing our best to provide accurate timing estimates based on the current dependencies. We’ll keep updating you every two weeks, which we believe is a fair and manageable rhythm, the next update is due on Thursday 28 August.
If you are unhappy with this approach and continue to have concerns regarding our communication, please use our formal complaints process Compliments & complaints
Please see table of works attached and timetable for occupation below, we are not anticipating any further delays to this timeline.
- Works completed and documented – w/c 25th August
- Internal registration process completed – w/c 1st September
- PC – w/c 1st September
- Serve notice on block C low rise – w/c 8th September
- Apply for registration – w/c 8th September
- Registration achieved - w/c 15th September
- Serve notice on block B high rise – w/c 15th September
*That registration dates depends on the outcome of our review*
Thank you for your understanding and patience as we work to complete this project.