Update 04/06/2025

Good afternoon

We explained in our last update that we were awaiting several key items from Mulalley to enable us to achieve practical completion.

We have received some of the documents from Mulalley and also through commissioning our own inspections. There is one outstanding item required on the lift maintenance certification which Mulalley are rectifying. We are waiting confirmation from Mulalley that they have resolved this item. We are discussing partial possession with Mulalley because we are keen to take practical completion of block C and await their response.

For block B, we had 48 outstanding items with Mulalley. Some of these items have now been received but some remain outstanding. We are identifying alternative options and will start to instruct their completion ourselves this week. Whilst we can’t put a timeframe on how quickly this information will become available, we will provide another update on progress next week.

Our next update will be sent by 11 June 2025 but please do let us know if you have any queries.

We have had some queries around the offers we have made to cover some of the costs incurred due to the delay, we will add a breakdown on Engagement HQ.

Kind regards

Richard White – Executive Director of Development

Luke Chandler – Director of Delivery

Vikki Walker – Director of Sales and Marketing

Share Update 04/06/2025 on Facebook Share Update 04/06/2025 on Twitter Share Update 04/06/2025 on Linkedin Email Update 04/06/2025 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>