2 April update
We still haven’t received the outstanding gas certificates as we have mentioned previously, we are unable to take PC without these in place. Having been advised last week that these certificates would be issued, we have now determined that Mulalley do not have them yet from their sub-contractor and they anticipate being in receipt of them by Monday 7 April.
Once we are in receipt of the gas certificates, we can begin to discuss potential practical completion dates with Mulalley. We still take the view that while the full suite of documentation for the high-rise buildings is not a prerequisite to taking PC, we also need to satisfy ourselves on matters such as fire safety before we take PC. This is because Mulalley is not contractually obligated to provide this support, which presents a potential risk.
We will provide another update by Tuesday 8 April.
Kind regards
Vikki Walker – Director of Sales & Marketing
Luke Chandler – Director of Delivery | Development

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends