26 March update

Good afternoon

Further to our previous update, we are sending you the below summary or the outstanding items ahead of taking practical completion and for occupation of block C at Greenside.

There are still actions outstanding from Mulalley. For block C these are:

  1. Certification – gas safety, emergency lighting and dry riser certification needs to be updated
  1. Heat Network - As previously advised, there was an issue with the commissioning of the heat network and how it relays usage data to the building management system. Mulalley have not been able to fully resolve this, however the heating and the hot water within the apartments is working satisfactorily. We are fully aware of how important it is for you to occupy your homes; we have therefore taken a view that we can resolve this matter once you are in occupation.
  1. Preoccupation FRA - There are some minor outstanding actions following the pre-occupation FRA, which relates to communal areas, this will not delay completion or affect individual apartments.
  1. Mulalley awaits highways department approval to the S278 plans. This issue will not be resolved prior to practical completion, and we will still be able to occupy. This will mean no access to the lower car park, and we will contact those affected separately.

For Block B, the document controller completed their review of the drawings linked to the project and the actions are being collated to be returned to Mulalley. Whilst a significant amount of documentation has been reviewed, there are other major elements of the pack to be audited before we can submit for registration. We anticipate this will take a further 8 weeks from PC.

Mulalley have no contractual requirement to supply the level of documentation we need to be able to submit for registration, this is because the development was contracted before the legislation came into force. We feel it important to be transparent about the potential risks and we must be satisfied that the documentation is to the standard that our business and the regulator requires.

For taking PC and occupation of block C, we are 24 hours off having a clearer view on a timeline and so will provide you with this by Friday 28 March.

We have had a number of questions asked, we will respond to these by adding them to the frequently asked questions section of the webpage here.

Kind regards

Vikki Walker – Director of Sales & Marketing

Luke Chandler – Director of Delivery | Development