Update 5th November 2024

Please see below our latest update outlining progress

Updates from the Construction team

The following activities have taken place since the last update:

  • FRA (Fire risk assessment) has successfully signed off all items
  • Lift inspection took place week commencing 21st October 2024, the inspections are now complete and signed off for use. The lifts will be maintained monthly.
  • All Planning notices have been successfully discharged by Croydon Council.
  • We currently await the building warranty sign off and documents.
  • As we still await some essential documentation, our development team have advised they expect practical completion by the end of November 2024. Please note, this is an estimated date and is when Southern Housing will receive the building from the contractors, this is not when we are able to serve you notice to complete and occupy.

Given the delay to practical completion, this will also delay the timeline to register this development with the building safety regulators. As such we now are estimating this development may not be ready for you to move into until May 2025. If we can however complete the process sooner, we’ll let you know immediately.

Webpage / engagement platform

You can now use this webpage to ask us questions and read our responses to other people's questions. If you have a question, you do not want published, please contact the team directly, or use the webpage and let us know you'd like us to respond privately, and it will remain hidden. Questions are only published when we respond. The requirements to sign up are minimal but if you have any difficulty, please email us at sales@southernhousing.org.uk

The advantage of the webpage is that it keeps all the information in one place for you to look at in your own time. We’ll add more information as it becomes available and in response to your requests.

The webpage currently contains the following features:

  • General information about the development
  • Your questions – for you to add questions and read what others have asked
  • Updates - contains milestone updates.
  • Who’s listening – details of key contacts
  • Progress – a timeline of key milestones
  • FAQs – Frequently asked questions and our responses.
  • Document library – for brochures, archived FAQs etc
  • Photos

Next update

The next update will be sent to you by 30 November 2024.

You can contact us by email at sales@southernhousing.org.uk at or by using the webpage ideas feature (scroll down to tabs at bottom of page and choose ‘Ideas’).

Share Update 5th November 2024 on Facebook Share Update 5th November 2024 on Twitter Share Update 5th November 2024 on Linkedin Email Update 5th November 2024 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>