Update 30/06/2025
We're writing with the latest progress update for Fount Spring Place.
There are still a few items outstanding before we can achieve practical completion (PC) and submit the building safety registration.
Three of these items are with the developer, Thornsett: the fire stopping register, servicing agreements, and confirmation of fire stopping in the lifts. Our Director of Construction is actively pursuing these, and we expect to receive them imminently. Separately, we are also working through the reports from the recently completed fire risk assessment.
We now expect to achieve practical completion and register the building at the end of July. This is dependent on receiving the final items from Thornsett and our satisfaction with the fire risk assessment reports.
We sincerely apologise that we're still not able to move you into your new homes and this does mean completions won’t happen in July as predicted, we do appreciate how frustrating this and will provide another update by 31 July 2025.
If you have any questions relating to your personal circumstances, please do not hesitate to contact your progressor, Joanne. If you have any questions relating to construction delays, then please submit them via the questions tab on this webpage.