Please find below an update on progress at Fount Spring Place, we are sending this update early as we have received more information on progress.

There are two main items outstanding and preventing practical completion:

Fire stopping records - we have now approached the third-party provider directly for these

Fire safety signage that affects the communal areas to close out from actions raised in the initial Fire Risk Assessment

Once we receive these items we will then be in a position to request the final Fire Risk Assessment.

We have put together the following predicated timeline to occupation:

15 August - We anticipate the above will be closed out and FRA report received

29 August – Practical Completion

1 September - Internal building safety team sign off for submission to the Building Safety Regulator

12 September – BSR Submission reference received

15 September – Serve notice to complete – 10 day notice to complete and occupy

29 September – Occupation

We hope this provides some clarity around what items are outstanding and the timeline to occupation. If you have any queries, then please do not hesitate to contact us. We will provide another update by 20 August 2025.

Many thanks

Share Update 25/07/2025 on Facebook Share Update 25/07/2025 on Twitter Share Update 25/07/2025 on Linkedin Email Update 25/07/2025 link
#<Object:0x00000000571ae4e0>