Update 22.08.2025

Thank you for your continued patience, regarding the delays at Banstead Road. We still awaiting some key items to be closed out relating to the building safety works, and there is still some building safety documentation needed before we can submit to our internal Building Safety Team for sign-off. These items include:

:

  • Recommended for fire safety signage to be installed in the communal areas.
  • To receive the fire stopping reports and review these.
  • Proof of servicing from Thornsett for the Operation and Maintenance Manual. Thornsett have confirmed that servicing has been completed and have committed to providing a service report, which we will use for submission to the Building Safety Regulator (BSR).
  • The Fire Risk Assessment (FRA) identified a low-risk issue due to the riser cupboard keyholes. We are seeking confirmation that either:
    a) no further action is required, or
    b) installing a blanking plate inside the riser cupboard will sufficiently mitigate the risk.
  • Lift Witness Testing Report – This is pending following the completion of some identified snagging items.

Taking the above into consideration, below is an anticipated timeline to occupation:

W/C 8th September –Technical team to check all received documentation and prepare the final building safety pack for sign off

W/C 29th September –Building Safety team to review building safety pack for sign off

W/C 13th October – Practical completion (PC) and building safety registration submission

W/C 20th October – Building safety registration to confirm receipt and provide reference

W/C 27th October – Building safety registration reference received to serve notice to solicitors

W/C 27nd October – 10 day notice given to solicitors to fix completion date for occupation

The above dates are indicative based on the current situation and subject to receiving all documents and those being satisfactory to submit for BSR registration.

We are committed to providing honest and transparent updates and will continue to keep you informed on progress as we move towards the final items being resolved and us taking PC. The next update will be on or before 8th September.