Update 19/02/25

Please find below our latest update on Fount Spring Place:

Practical completion is now predicted for March, due to the finalisation of some outstanding documents required for building safety registration, our building safety team continue to review documents as they are received in preparation for submission once we achieve practical completion. Occupation is still predicted for May 2025.

Good news, we have received a revised EWS1 form and report from fire our safety consultants, Hydrock, this replaces the one previously issued by Tri-fire.

For questions regarding your individual circumstances or general enquiries about the sales process, please continue to contact your progressor, Alisha. For questions specifically related to construction delays, please reply to this email, or submit your questions via the questions tab on this webpage.

Our next update will be Thursday 13 March 2025.

Share Update 19/02/25 on Facebook Share Update 19/02/25 on Twitter Share Update 19/02/25 on Linkedin Email Update 19/02/25 link
#<Object:0x00007f39c855b258>