Update 15/04/26
I am writing to provide an update on the status of the lift works and the subsequent steps toward completion.
Please see the below timeline for works schedule
- Remaing Lift parts were successfully delivered from overseas on Tuesday 14th April.
- Installation works are booked in for Wednesday 15th April and aim to be completed by close of business 17th April 2026.
- Our independent consultant is due to return to site on Monday 20th April 2026 to conduct a final inspection and sign off of the lifts.
- Report to be issued for internal reviewed by our building safety team on 24th April.
- Internal team confirm if this is accepted by 1st May
- Submit to the building safety regulator on 8th May.
- BSR registration confirmation within 2 weeks of submission.
- Handover and notice for occupation End-May 2026.
I hope this timeline gives you some comfort that we are progressing. We will provide you with a further update on Wednesday 29th April to confirm if we are on track with the above schedule.
We thank you again for your patience.