Update 08/09/2025

Please find below the latest update on progress at Fount Spring Place:

We advised in our last update that we were awaiting some key items to be closed out relating to the building safety works, and that there was still some building safety documentation needed before we can submit to our internal Building Safety Team for sign-off. Updates on these items below:

  • Fire safety signage to be installed in the communal areas – This has been completed and evidence provided to Hydrock (fire safety consultant) who will use this to update the Fire Risk Assessment. There was one last piece of evidence required for the fire alarm system arrangements. This has now been received and sent on to Hydrock for review.
  • To receive the fire stopping reports and review these - We anticipate the report will be received on Friday 12 September and will then be reviewed.
  • Proof of servicing from Thornsett for the Operation and Maintenance Manual - The servicing documentation we’ve received is not clear we have asked the contractor, Thornsett, to provide greater clarification on this item.
  • The Fire Risk Assessment (FRA) identified a low-risk issue due to the riser cupboard keyholes - We are reviewing what activities need to be undertaken; however, we do not believe this will impact on our ability to take practical completion or occupy.
  • Lift Witness Testing Report – This is pending following the completion of some identified snagging items, these are due to be completed on 10 September.

We do not anticipate any changes to the previously communicated timeline which is subject to receiving all documents and those being satisfactory to submit for BSR registration.

The next update will be on or before 26 September.

Share Update 08/09/2025 on Facebook Share Update 08/09/2025 on Twitter Share Update 08/09/2025 on Linkedin Email Update 08/09/2025 link
#<Object:0x0000000021825f70>