Update 08/01/2026

I am writing to provide an update on the registration process for Fount Spring Place.

We have reached a significant milestone with the completion of all Fire Risk Assessment actions. However, the associated certificates and documents are still undergoing review by our technical team. This means we are not yet in a position to submit the Building Safety Registration as previously advised.

Although the following work is not required prior to registration, our team has identified that the riser cupboard doors need to be replaced. Before our internal Building Safety Team can accept the scheme for registration and handover, we must have an agreed cost and programme of works. We have already requested this information from the sub‑contractor, and once received, we will finalise the submission pack for review and approval.

Revised timeline:

  • 2 February: Submission to the Building Safety Team for review
  • 6 February: Approval meeting for Building Safety submission
  • 9 February: Submission to the Building Safety Regulator (BSR)
  • Week commencing 16 February: Expected BSR approval to occupy

We are sorry to have to communicate a further delay and fully recognise the impact this has, we sincerely appreciate your continued patience as we work through these final steps.