Update 06/03/2026

I am emailing with an update on progress at Fount Spring Place.

There were 2 items outstanding before we could proceed with registration as follows:

  • Riser cupboard doors – we are expecting the quote and programme for the riser cupboard door replacement works today.
  • Lifts

Following the inspection, work took place on site on Thursday 5 March and we await sign off from our independent surveyors, RPS. We expect this will happen next week.

There is one piece of paperwork (Key Building Information) that requires updating to reflect the works we have been completing. We have commissioned our employer’s agent to complete this.

If we can obtain all the above by 13 March, we would expect the building safety submission to be submitted the week after.

Thank you for your continued patience. I will be in touch again as soon as the above information is received but by no later than Friday 13 March.