Please find the latest update on progress at Fount Spring Place.

The pre-occupation fire risk assessment was successfully undertaken, and the reports were issued last week. These reports set out a few necessary actions that we must complete before we can register and occupy the building.

The required actions primarily involve:

  • Some minor repairs and remediation works to doors
  • Minor amendments to required signage
  • Small-scale works to the fire stopping

We have shared these actions with the contractor today and are currently discussing timeframes for this work to be completed.

We do not believe that the above works will affect the current predicted timeline, and January 2026 is still the expected date for occupation.

We will provide another update by 19 November 2025.