Update 02/04/2026

I am writing to provide an update on the status of the lift works and the subsequent steps toward completion.

The necessary part for the lift has been ordered; however, due to manufacturing delays, delivery is now expected at the end of next week. We have scheduled the installation for the week commencing 13 April. Providing there are no further logistical delays, we anticipate the lift will be fully installed and signed off by our consultant by 17 April.

Once the lift is operational and signed off our Building Safety Team will conduct a final inspection of the building safety case. Once internally cleared, the documentation will be submitted to the Building Safety Regulator for the final sign-off required for occupation.

We understand how important this timeline is for you. We will provide you with a further progress update on Wednesday 15 April to confirm if we remain on track with the delivery and installation schedule.

Thank you again for your patience.