Update 07.11.2024
Good afternoon
Thank you for your continued patience concerning Wharf 21, please find below the latest update from our construction team.
We are pleased to be able to tell you that we have received building control sign off for the whole of block G, along with the NHBC warranty certificates.
Updates from the construction team
Block H:
IFI items continue to be worked through and completed
Block G1
IFI items continue to be worked through
Fire risk assessment due - This was booked in for Friday 1st November and we are awaiting the report
Block G2
The quality control checks are still ongoing, our clerk of works is on site this week and hopeful he will close the remaining items out
IFI items continue to be worked through and completed
Final inspection date before lock and leave to be confirmed
Building control sign off – We have had confirmation that building control has been signed off
Fire risk assessment due – This was booked in for Friday 1st November and we are awaiting the report
Externals/general
Final work to the Level 1 and level 6 terraces is completed
The External Wall System (EWS1) inspection is complete, and we received the ESW1 certificate for G1 & G2 and this has been shared with our solicitors.
Based on the outstanding works, practical completion is still on track for 27th November 2024. This is the date that the development will be handed over to Southern Housing, it is not the date that you will be able to occupy the properties.
Building Safety Regulation (BSR):
This review is still on going and we are waiting for certain documents to be revised ready for further review.
We believe that the provisional March occupation remains achievable.
Next update
The next update will be sent to you by 21st November 2024.
You can contact us by email at sales@southernhousing.org.uk at or by using this webpage
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends