Update 05.12.2024
Thank you for your ongoing patience with the Wharf 21 development. Please find below the latest update.
Updates from the construction team
Blocks H, G1 & G2
- Work is due to be completed on the door inspections by the end of this week
- We require IFI to issue a full Fire Risk Assessment and this is due on 11th December subject to the doors being signed off as above
- There is a final walk through of the units scheduled for Thursday 5th December with HG construction and our own construction team
Due to outstanding documentation and site closures over Christmas, we are anticipating that we may not be build complete until January 2025, we still anticipate occupation in March 2025.
The next update to you will be on 16th January 2025, however if we take practical completion before this date, we will of course let you know straight away.
If you have queries relating to your specific circumstances you can continue to contact your sales progressor, Alisha. You can contact us regarding development updates via email or via the questions tab on this page.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends