Following on from our previous update, I am pleased to confirm that the fire curtain has been installed and will be commissioned this week.
We have been informed of a recent leak at the development. The leak has been located and repaired, and any resulting decorative damage is currently being addressed. This will not impact our ability to achieve practical completion, but we wanted to provide you with this information for full transparency.
Our building safety team continue to work through the documentation for the building safety submission and there are still some items outstanding. The process to register requires us to submit key data to the Building Safety Regulator to obtain permission to occupy the building. Once this is done, the Regulator can request a Building Safety Case Report at any time. This report must provide clear evidence that the building is safe. Failure to present this could result in serious regulatory penalties being imposed. Therefore, it is Southern Housing’s policy that we will not submit the building for registration until we have assurance that we have all the information we need to create our Safety Case Reports.
Once we have the required paperwork we will take Practical Completion. We are still forecasting occupation for late April; however, we want to inform you that occupation could be delayed until May if we do not receive the necessary paperwork promptly to be able to register the building.
We will provide our next update by 25 April 2025. If you have any questions regarding your individual circumstances, please contact your sales progressor, Alisha. For questions about construction delays, please submit them via the questions tab on this webpage.