Update 04/02/2025
Please find below an update on New Kent Row:
We are still awaiting the fire curtains on the bin store doors at ground floor level, which are currently being fabricated as part of the fire stopping works mentioned in earlier updates. We still anticipate achieving practical completion mid-February.
Preparation for building safety registration is ongoing whilst we wait on practical completion.
We will provide our next update by Friday 21 February.
You can continue to raise questions via sales@southernhousing.org.uk or via the questions tab on this webpage.