Update 19/09/2025
Good afternoon,
I am emailing to provide you with an update on progress at Holmhurst Gardens.
I am sorry to inform you that the completion of plots 90-96 has been delayed again. This is due to the final commissioning of the air source heat pumps. This affects certificates being issued which delays the final building control sign off, we must have this to accept handover of the homes.
The snagging of your property is now scheduled to take place on 7 October 2025. Once this is complete, we will be in a much better position to provide you with a new completion date.
We sincerely apologise for this further delay. We will continue to get updates from the team and will be in touch again by Friday, 10 October 25, with another update.
Thank you for your contribution!