Update 12 July 2024

Update from 12 July 2024

We have now completed the procurement process and have selected a contract to carry out the recommended works. Due to the contract value, we now have to take this to our board for approval. Once approved we are anticipating to have the works started by early October.

The works are due to take approximately 20 weeks to complete ready for reinspection and occupation sign off.

As a result of the above we are anticipating occupation to be in the Spring of 2025, we will be in a position to offer better dates once work commences. If you have mortgage offers expiring you should speak to your broker to look at your options. As usual if you wish to continue with the purchase and have to seek new mortgages, we will cover mortgage arrangement fees and valuation fee which will be in the form of a deduction from your completion statement and will be subject to proof of payment.

For those no longer wishing to wait, you should contact your solicitor to discuss options to rescind and your entitlement as a result. We will not be offering any form of goodwill or compensation.




Share Update 12 July 2024 on Facebook Share Update 12 July 2024 on Twitter Share Update 12 July 2024 on Linkedin Email Update 12 July 2024 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>