Update 20.11.2025

Following the meeting on Monday with our Building Safety Team, there are still items outstanding and we therefore do not anticipate being able to achieve occupations in December.

An update on the works and documentation:

  • Works to the fire doors are all complete, checked and signed off
  • We’ve had the FRA and fire stopping close-out reports – these are with our internal team for review.
  • Following our internal maintenance contractors checks some additional work on the smoke vents has been identified. We’re in the process of organising for this work to be completed.
  • HIU commissioning certificates – we received the full set of certificates, but some didn’t have the full address and postcode on them, so we’re had to request these are re-issued
  • The CHP and Boiler have both been commissioned however some remedial works have been identified to both. The Boiler works were previously booked for 13/11; this had to be rescheduled to today due to staff availability. We’re waiting for a date for the CHP works.
  • The UPS is booked in for commissioning checks on 28/11.

We will provide a revised table detailing all outstanding items and any further information in our next update on Tuesday 25 November. We still anticipate occupation in January.