Update 14/11/2024
Good afternoon
Thank you for your continued patience on our Corner Place development. The latest update is as follows:
We are pleased to confirm that the contractor Elements, have started work onsite. The works are estimated to take around 20 weeks to complete ready for reinspection and sign off.
As you are aware, due to the height of the building this requires registration with the Building Safety Regulator, in line with building safety regulations that came into force in October 2023. We anticipate receiving registration to allow occupation in Spring 2025.
Next update
We will provide another update with progress on site by the end of January 2025.
If you wish to discuss your individual circumstances you can contact your sales progressor, Alisha. You can also contact us by email at sales@southernhousing.org.uk or via the link to the webpage above.
Many thanks
Lisa