Update 14/05/2025

We are pleased to confirm that we have now received the EWS1 form for Corner Place.

On opening the building for inspection, Elements, the contractor working on site, have identified that remedial works are required to the lift shafts and now anticipate that works will be complete by 31 July 2025. This means that occupations will be pushed into September.

We are sorry to communicate a further delay; we appreciate your patience and thank you for your continued understanding.

If you have any questions relating to your personal circumstances, please continue to contact your sales progressor. If you have any queries regarding the construction delay then please reply to this email or submit a question via this webpage.

Share Update 14/05/2025 on Facebook Share Update 14/05/2025 on Twitter Share Update 14/05/2025 on Linkedin Email Update 14/05/2025 link
#<Object:0x000000004b7c5dd0>